Inferred gen-set demand for this project. Headline rollup is shown publicly; the per-unit equipment class, operator-practice library citations, and the full methodology trail are in the operator console.
| Proj # | AESO Name | MW (STS) | Type | Fuel | In-Service | Bucket | Est. value | Equipment class |
|---|---|---|---|---|---|---|---|---|
| P2533 | Greenlight Gas | 466 MW | Gas | Gas | 2028-06-01 | EPC-DIRECT | $280M – $466M | Heavy frame turbines (GE 7HA, SGT-8000H, M501JAC class) — typically EPC-direct |
| P2796 | Greenlight U2 Gas | 466 MW | Gas | Gas | 2028-06-01 | EPC-DIRECT | $280M – $466M | Heavy frame turbines (GE 7HA, SGT-8000H, M501JAC class) — typically EPC-direct |
| P2797 | Greenlight U3 Gas | 466 MW | Gas | Gas | 2028-06-01 | EPC-DIRECT | $280M – $466M | Heavy frame turbines (GE 7HA, SGT-8000H, M501JAC class) — typically EPC-direct |
| Total estimated package value: | $839M – $1398M | |||||||
Per-class value bands: Heavy frame $600–$1000/kW; Aero-derivative $700–$1200/kW; Reciprocating $800–$1500/kW. Cancelled rows shown for transparency but excluded from totals. Value is for the gen package only (turbine/engine + switchgear + controls); does not include site civils, fuel infrastructure, or grid interconnect.
| Step | Finding | Source |
|---|---|---|
| Project classification | hyperscale_ai | pembina |
| Operator-practice lookup | Pembina/Kineticor JV (Greenlight) uses utility-scale combined-cycle gas turbines. Heavy-frame, EPC-direct from GE/Siemens/Mitsubishi — not packager territory. | AESO Generation queue rows P2533, P2796, P2797 (Greenlight Gas units, 466 MW STS each). |
| Backup-gen sizing (hyperscale_ai) | 827 units × 2.5 MW = 2068 MW total | Tier 3/4 hyperscale: ~100% of IT load in 2.5 MW packages, N+1. |
| BTM prime — confirmed | 3 thermal generation row(s) linked in AESO Generation queue, totaling 1398 MW STS | AESO Long-term Adequacy report — power_allocations rows: P2533, P2796, P2797 |
| Proj No | Allocation | Type | MW | Stage | Status | In-Service | Link via |
|---|---|---|---|---|---|---|---|
| P2936 | GLDC Load Phase 1.1 | Data Load | 970 MW | Stage 2 | Active | 2027-05-01 | projno_alias |
| P3151 | GLDC Load Phase 1.2 | Data Load | 830 MW | Stage 2 | ISD Under Review | projno_alias | |
| P2533 | Greenlight Gas | Gas | 466 MW | Stage 3 | Active | 2028-06-01 | token_overlap |
| P2796 | Greenlight U2 Gas | Gas | 466 MW | Stage 3 | Active | 2028-06-01 | token_overlap |
| P2797 | Greenlight U3 Gas | Gas | 466 MW | Stage 3 | Active | 2028-06-01 | token_overlap |
MPI registry source →
Schedule: Completion by 2029
Each fact on this page is only as fresh as its source scrape. Green = refreshed in the last 24 hours. Amber = 24-48 hours. Yellow/red = 2+ days. If you're making a procurement decision off something here, the freshness column tells you whether to verify with the underlying agency before acting.